Title: Big Ben Refurbishment Costs Double
Post by: John R on September 29, 2017, 17:57:43
http://www.bbc.co.uk/news/uk-politics-41444415

Repair costs for the Elizabeth Tower in the Palace of Westminster have now doubled to an estimated £61m, parliamentary authorities have said.
The project is more complex and extensive than originally thought, when the estimate of £29m to £45m was made.
While there were "unique challenges" in work on a historic site, Parliament said it was disappointed at the rising bill and would launch a review.


Maybe the government will now "pause" the project, and will subsequently sign off a rescoped project, with only two faces restored to use, and the chimes replaced by innovative technology (i.e. a loudspeaker playing a recording).


Title: Re: Big Ben Refurbishment Costs Double
Post by: SandTEngineer on September 29, 2017, 20:46:36
Got their GRIP 4 cost estimates a little bit wrong then...... ::) :P

http://www.bbc.co.uk/news/uk-politics-41444415

Quote
Repair costs for the Elizabeth Tower in the Palace of Westminster have now doubled to an estimated £61m, parliamentary authorities have said.

The project is more complex and extensive than originally thought, when the estimate of £29m to £45m was made.
While there were "unique challenges" in working on a historic site, Parliament said it was disappointed at the rising bill and would launch a review.

Big Ben chimed for the last time in August pending the work beginning.

The rising cost was announced as Parliament confirmed it had appointed construction firm Robert McAlpine to carry out the renovation, which could take up to four years, following a tendering process.

The authorities said the revised figure followed more detailed and technical assessment of the 160-year-old Tower's condition, including the state of stonework and the cost of removing and repainting the metal in the tower and reglazing the clock face.

Big Ben will chime only on New Year's Eve and other special occasions.

More extensive ground works will be required in the Palace of Westminster, due to the quantity of pipes and other utility-related infrastructure under the surface, to support the scaffolding required.

While the estimated cost of the work has risen from £29m to £44m, the level of contingency funding to be put aside in case of "unexpected events" has gone up from £5.8m to £17.2m.

The authorities also said they had transferred the cost of fire safety work, due to be carried out as part of another project and already budgeted for, to the restoration of the tower.

They said they had "expressed their disappointment in the cost increases, and the unreliability of the original estimate" and "instructed officials to provide regular updates on progress".

"In advance of tendering contracts, the initial high level estimates were set at a lower level to avoid cost escalation from the market," they said in a statement.

"Subsequent estimates, using better data and more extensive surveys, better reflect the true likelihood of the costs. We believe that we now have a more accurate estimate of the cost of the works and will report regularly to the committees on the progress of work."

The news that Big Ben would not sound again before 2021, except for special occasions such as New Year and Remembrance Sunday, prompted criticism from Theresa May and other MPs.

The House of Commons said it would look again at the duration of the project and the scope for hearing the bell's famous bongs more often.


Title: Re: Big Ben Refurbishment Costs Double
Post by: broadgage on September 30, 2017, 14:20:19
Perhaps the project managers could get a job with network rail.


Title: Re: Big Ben Refurbishment Costs Double
Post by: Electric train on October 01, 2017, 08:02:48
Perhaps the project managers could get a job with network rail.

The Big Ben PM's ultimately work for the same client as the NR PM's ..................... and the client the same lot who are making a hash or running the country  ;D a client that never gets past GRIP 1 and see GRIP 8 as a mystical beast


Title: Re: Big Ben Refurbishment Costs Double
Post by: TaplowGreen on October 01, 2017, 10:03:12
Perhaps the project managers could get a job with network rail.

They probably used to work for Network Rail looking at those figures - remember that the standard public sector technique for dealing with under performance is to move those concerned onto another job!  ::)



This page is printed from the "Coffee Shop" forum at http://gwr.passenger.chat which is provided by a customer of Great Western Railway. Views expressed are those of the individual posters concerned. Visit www.gwr.com for the official Great Western Railway website. Please contact the administrators of this site if you feel that content provided contravenes our posting rules ( see http://railcustomer.info/1761 ). The forum is hosted by Well House Consultants - http://www.wellho.net