Great Western Coffee Shop

Journey by Journey => London to Didcot, Oxford and Banbury => Topic started by: SandTEngineer on July 06, 2018, 22:37:20



Title: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 06, 2018, 22:37:20
Just to let everybody know that another ex-WR panel signalbox closes early Saturday morning 07 July 2018.  Oxford Panel, as it is known, was opened on 14 October 1973 and was one of the smaller such WR control centres.  The new signalling will be commissioned in three stages and will be controlled from the Thames Valley Signalling Centre at Didcot:

Stage 1
FROM Monday 9th July 2018 – New Signalling commissioned from Didcot as far as temporary stop block approaching Hinksey South Junction to include Morris Cowley Branch to enable the Morris Cowley Plant to be accessed.

Stage 2
FROM Monday 16th July 2018 – Further signalling commissioned at the Didcot end to include access to and from Oxford Station Platform 4 from the south only. Note; From Hinksey South, only the Down Oxford and Down Oxford Relief are commissioned to enable trains to arrive and depart Oxford platform 4.

Stage 3
FROM Monday 23rd July 2018 - Main and Final Commissioning.

Overview of Oxford Phase 1 Changes
■ Oxford Panel Signalbox area of control will be resignalled and remodelled with
control of the area transferred to a new Oxford IECC Workstation located in
Thames Valley Signalling Centre (TVSC), Didcot
■ The signal prefix ‘OX’ will be withdrawn and replaced with ‘OD’ for the new Oxford
Workstation area
■ Train detection will be provided by AzLM axle counters
■ There will be a number of connections newly referred to as junctions
■ Up Passenger Loop between Wolvercot North and Oxford North Junction will
be renamed the Up Oxford Relief, with a 90mph connection and maximum line
speed
■ Down Passenger Loop extended beyond Oxford North Junction to Wolvercot
North Junction and will be renamed the Down Oxford Relief. Line speed and
turnout increased to a maximum 90mph permissible line speed
■ A new connection with the Up Oxford Relief will be provided north of Oxford
Station that will allow trains to arrive and depart Bay Platforms 1 & 2 whilst
parallel moves are also taking place to and from platform 3 via newly aligned
connections north of Oxford station referred to as Oxford Station North Junction
■ The Down Carriage Sidings at Oxford will be renamed the Down Oxford Sidings.
The sidings will be remodelled and a new Down Turnback Line will be introduced
able to accommodate a train equal to 260 metres in length.
■ The single line arrangement between Oxford North Junction and Woodstock
Road Junction will be replaced by extending the Up Bletchley and Down Bletchley
lines into two individual bi-directional lines
■ Bi-directional working will be introduced on the newly named Up and Down
Oxford Lines between Wolvercot North Junction and Appleford and between
Appleford and Didcot Station on the Up Oxford
■ A new platform starter signal will be introduced at the Didcot end of Oxford
Platform 4
■ Tackley Ground Frame will be recovered and control of the two sets of crossover
points will be controlled directly from the new Oxford workstation
■ The Morris Cowley Branch will be re-signalled and worked in accordance with
TCB Single Line Regulations with the token machines being recovered
■ The Up Carriage Sidings at Oxford will be renamed Up Oxford Sidings. The hand
points will be converted to power operation and controlled by the Signaller at
Oxford Workstation
■ New ground position light signals will be provided at the exit of each Up Oxford
Siding
■ Following resurfacing at the north end of Oxford Platform 3, the platform will be
re-opened to its full length of 274 metres


Title: Re: Oxford Area Resignalling 2018
Post by: IndustryInsider on July 06, 2018, 23:37:17
A massive increase in flexibility signalling wise, and when (if) Phase 2 is completed there will be further improvements including a new Platform 5 and bi-directional signalling as far as Tackley.  Long overdue at Oxford which has one of the most restrictive layouts you can imagine for a station of its size and importance.  The new connection to allow parallel moves to/from Platforms 1/2 and Platform 3 will save thousands of delay minutes annually alone.  The removal of tokens on the Morris Cowley branch will make it much easier to introduce passenger trains to the Business Park and Science Centre in the future.

There are downsides though as communication between station/sidings staff and Signallers at Oxford will become much harder as there will be no direct radio link, though the recent reinstatement of Area Operations Managers (AOM's) will help in that regard.


Title: Re: Oxford Area Resignalling 2018
Post by: ellendune on July 07, 2018, 08:02:36
 The handout from NR (https://cdn.networkrail.co.uk/wp-content/uploads/2018/06/Didcot-parkway-Oxford-and-Banbury-summer-works.pdf) has  on page 3 a "Map of works north of Oxford station". This mentions the Sheep wash underbridge.  Does anyone here know what works are being done to that?



Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 07, 2018, 09:13:36
A massive increase in flexibility signalling wise, and when (if) Phase 2 is completed there will be further improvements including a new Platform 5 and bi-directional signalling as far as Tackley.
Phase 2 has been designed into the new system so only requires addition trackside of the physical extra signals and points.  Not sure if it will actually happen though......


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 07, 2018, 09:46:59
Also worth noting that all of the new signals (except those between Wolvercote Junction and Ahnyo Junction) are 4-aspect instead of the previous 3-aspect.  This allows closer spacing of the signals, hence shorter signal section lengths and much reduced headway and therefore, increased line capacity.

The upgrade to the signals between Wolvercote Junction (excl) and Ahyno Junction, and the implementation of full bi-directional signalling, have been designed in and included, for Phase 2.


Title: Re: Oxford Area Resignalling 2018
Post by: bobm on July 07, 2018, 11:26:18
From the train describers at Oxford (courtesy of OpenTrainTimes)

(http://www.mbob.co.uk/rforum/oxpanel2.png)


Title: Re: Oxford Area Resignalling 2018
Post by: Oxonhutch on July 07, 2018, 21:40:20
Won't shed too much of a tear. 'Twas pretty dire 1978-81 and only a cosmetic overhaul since then [that subway!] - prior to Chiltern's arrival.


Title: Re: Oxford Area Resignalling 2018
Post by: GBM on July 07, 2018, 22:44:37
Just to let everybody know that another ex-WR panel signalbox closes early Saturday morning 07 July 2018. 


Thank you so much for such detailed information.  Muchly appreciated (even tho' it's a long way from my area)...
It's good to see detailed information passed for all to see.
Thank you again


Title: Re: Oxford Area Resignalling 2018
Post by: Electric train on July 08, 2018, 09:43:46
Won't shed too much of a tear. 'Twas pretty dire 1978-81 and only a cosmetic overhaul since then [that subway!] - prior to Chiltern's arrival.

The subway was subject to flooding, the pumps were a mare to keep going always getting silted up caked in line scale and a general pain in a*** to get up the stairs



I do believe the Oxford Panel was only intended as stop gap much like the old Didcot Panel


Title: Re: Oxford Area Resignalling 2018
Post by: 4064ReadingAbbey on July 08, 2018, 13:05:52
Adapted from a post in RailForums.co.uk...

From G. T. Moody's book Southern Electric (Ian Allan 1957), page 61:

Quote
In January 1935, the Southern Railway announced that £500,000 would be spent on improving and re-signalling the lines into Waterloo. The layout of the four lines from Hampton Court Junction was up, up, down, down as far as Waterloo "C" box, whence three up and two down lines continued to the terminus (this excludes the Windsor lines). Although it was the practice to divert an incoming train at "C" box to a route into the terminus which would cause the least interference with other up and down lines, the layout had become liable to cause delay, and with the steadily increasing traffic reorganisation had become necessary.
and
Quote
It was decided to construct a flyover at Durnsford Road, Wimbledon, the only suitable site, to carry the up local over the up and down through lines. Thence to Waterloo the four lines would be re-arranged to form up and down through and up and down local lines, with an additional up main through relief from Vauxhall to the terminus. Colour light signalling would be installed, with a power-operated cabin at Waterloo.
The flyover was constructed of steel girders, cased in concrete, and mounted on concrete columns. It was 2,174ft long, rising at 1 in 60 at the Wimbledon end, crossing the through lines on the skew and then falling at i in 45. Work on it commenced in September 1935.
The change to colour light signalling at Waterloo was made on Sunday, October 18th (1936). The new signalbox, on the up side, built mainly of concrete, contained 309 electrically-interlocked levers in three frames for main local, main through and Windsor lines respectively.

and most amazingly to modern observers...

Quote
The changeover was made smoothly; the 12.35am to Hampton Court was signalled out by semaphores and the 1.30am to Salisbury by colour lights.

If the times have been correctly interpreted (I assume - as the the original poster seems to have done - that 12.35 am is 35mins past midnight), one hour was needed in 1936 to change over the signalling...


Title: Re: Oxford Area Resignalling 2018
Post by: paul7575 on July 08, 2018, 13:42:08
Selective quoting?  AIUI from that section of Moody’s book the semaphore signalling was adapted over the course of almost a calendar year as the track layout was changed gradually, while the colour light system was installed and tested in parallel  (and presumably covered up), hence that short period of final changeover probably isn’t so surprising.

Also, given the number of platforms, Hampton Court and Salisbury trains would normally leave via different main lines, it doesn’t necessarily imply the whole station was done at once, or only stopped for that hour.  Just that the last remaining semaphore route was still available until 0035, and the first colour light controlled route became available at 0130.

Paul


Title: Re: Oxford Area Resignalling 2018
Post by: 4064ReadingAbbey on July 08, 2018, 20:16:06
Sorry, I don't know whether it has been selectively quoted or not.

Nevertheless, there is a startling difference between the length of time it took to do things then and now. The SR's Board made the decision in January 1935 the resignalling took place 21 months later.


Title: Re: Oxford Area Resignalling 2018
Post by: Worcester_Passenger on July 08, 2018, 21:27:36
Here is the full text:

Quote
In January, 1935, the Southern Railway announced that £500,000 would be spent on improving and re-signalling the lines into Waterloo. The layout of the four lines from Hampton Court Junction was up, up, down, down, as far as Waterloo "C" box, whence three up and two down lines continued to the terminus (this excludes the Windsor lines). Although it was the practice to divert an incoming train at "C" box to a route into the terminus which would cause the least interference with other up and down lines, the layout had become liable to cause delay, and with steadily increasing traffic reorganisation had become necessary. Signals and points were worked manually, with Sykes lock-and-block control, except that at West London Junction and Clapham Junction signals and points were operated on the low-pressure pneumatic system, with track circuiting. The celebrated "A" box, which spanned the lines outside Waterloo, contained 266 levers and dated from 1892.

It was decided to construct a flyover viaduct at Durnsford Road, Wimbledon, the only suitable site, to carry the up local over the up and down through lines. Thence to Waterloo the four lines would be re-arranged to form up and down through and up and down local lines, with an additional up main through relief from Vauxhall to the terminus. Colour-light signalling would be installed, with a power-operated cabin at Waterloo.

The flyover was constructed of steel girders, cased in concrete, and mounted on concrete columns. It was 2,174 ft. long, rising at 1 in 60 from the Wimbledon end, crossing the through lines on the skew and then falling at 1 in 45. Work on it commenced in September, 1935.

There was no platform at Vauxhall on the down main through and as this line would become the up main local reconstruction was necessary. The existing down main local platform was therefore closed on November 3, 1935, and demolished. The down main local was then slewed over and a new island platform built on the space thus made available; the latter was brought into use on March 9, 1936.

Meanwhile re-signalling had been going ahead, and a girder of 132 ft. span to carry the up inner home signals was erected outside Waterloo on the night of October 20, 1935. The new colour-light signals were three-aspect as far as Loco Junction (Nine Elms), where freight workings commenced, and then four-aspect to Hampton Court Junction on the main line, and to Clapham Junction on the Windsor lines. Many of them were mounted on lattice brackets.

Several innovations were introduced on this re-signalling scheme. All colour-light signals had small side aspects, for the benefit of drivers whose trains had drawn up close to the signals, and were promptly dubbed" pig's ears" by the drivers. At junctions the practice of providing a colour-light signal for each route was abandoned in favour of position-light junction indicators. Ground signals consisted of a white disc with red bar, floodlit at night.

Permanent way alterations between Vauxhall and Waterloo were carried out in stages at week-ends, but platforms 1 to 3 at the terminus were closed for relaying the approaches from May 8, 1936, and from 6 p.m. on the 15th platforms 4 to 6 were taken out of use for the same purpose. The new track layout was assembled and tested on spare land at Mitcham before being laid in at Waterloo. On Sunday, May 17, 1936, the lines from Waterloo to Surbiton were closed from 1 a.m. to 7 a.m., so that the flyover, re-arranged lines, and most of the new signalling could be brought into service.

The new signalling extended from Waterloo "B" box to Clapham Junction on the Windsor lines and to Malden on the main line. The change-over at Waterloo was wisely deferred until the summer train service was over, although the manual signalling had to be extensively altered.

As the station at Surbiton was being rebuilt, colour-light signals from Malden to Hampton Court Junction were not brought into use until June 28. Two new signalboxes were provided on this section; Surbiton (52 levers) and Hampton Court Junction (45 levers). The new box at Surbiton was the first of the" glasshouse" type, used in many later installations.
On weekdays from July 5, 1936, the suburban services were re-arranged so that trains from Waterloo to Dorking North and Effingham Junction were fast to Wimbledon, then calling at Motspur Park and all stations. From 5.7 to 7.7 p.m. they were fast to Motspur Park. A new service was put on from Waterloo to Motspur Park, calling at all stations and running every 20 minutes from 6.16 a.m. to 10.56 p.m.

The change to colour-light signalling at Waterloo was made on Sunday, October 18. The new signalbox, on the up side, built mainly of concrete, contained 309 electrically-interlocked levers in three frames for main local, main through, and Windsor lines respectively. The four track diagrams were of a new type, the tracks being shown as white lines on a black ground and the presence of a train indicated by two red lights. Route indicators of the theatre type were liberally provided, and on each platform a starting signal repeater showed" ON" or" OFF". Loudspeaker communication was provided to the down sidings. The changeover was made smoothly; the 12.35 a.m. to Hampton Court was signalled out by semaphores and the 1.30 a.m. to Salisbury by colour-lights.


Title: Re: Oxford Area Resignalling 2018
Post by: Electric train on July 08, 2018, 21:57:59
Sorry, I don't know whether it has been selectively quoted or not.

Nevertheless, there is a startling difference between the length of time it took to do things then and now. The SR's Board made the decision in January 1935 the resignalling took place 21 months later.

The rules and laws for construction were very different.   No appeasing Local Councils or residents, H & S Law far far less onerous, the Rules for working on the line compared to now they were virtually non existent, there was no "Product Acceptance" that we have today, testing and commissioning was not as rigorous as it is today, was possible then to hand signal trains even in the peaks.

And the biggest pain in the !!!! to engineers today is the whole tendering and contractual process that is in place now that would have been much simpler and quicker in the 1930's


Title: Re: Oxford Area Resignalling 2018
Post by: Red Squirrel on July 09, 2018, 10:43:29
And the biggest pain in the !!!! to engineers today is the whole tendering and contractual process that is in place now that would have been much simpler and quicker in the 1930's

Yes - the public sector seems to spend half their budget on ensuring that they get good value for money...


Title: Re: Oxford Area Resignalling 2018
Post by: stuving on July 09, 2018, 12:24:14
And the biggest pain in the !!!! to engineers today is the whole tendering and contractual process that is in place now that would have been much simpler and quicker in the 1930's

Yes - the public sector seems to spend half their budget on ensuring that they get good value for money...

But the same trend towards bigger documents, more planning (except for what actually goes wrong), and more cost in the contracts department has happened within the private sector. In some cases the company's structure and methods were set up for subcontracts within public contracts, but the impression I got was that this was seen as a more professional way of doing things.


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 09, 2018, 13:32:46
Well then, back to the topic title ::)   Stage 1 seems to have been successfully commissioned this morning (09 July 2018).


Title: Re: Oxford Area Resignalling 2018
Post by: martyjon on July 09, 2018, 14:07:34
Well then, back to the topic title ::)   Stage 1 seems to have been successfully commissioned this morning (09 July 2018).


.... till the "faults with the signalling system" start to occur when normal traffic resumes ....


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 12, 2018, 19:46:56
A small update.  Things seem to be progressing to plan with just a couple of minor signalling design modifications so far.  Out of interest there is a track map showing the non-signalling changes at the top of the drawing here: https://www.oxford.gov.uk/download/downloads/id/1839/east_west_rail_b90505b-drg-pwy3003.pdf


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 16, 2018, 09:24:06
Stage 2 commissioned to plan today (16 July 2018).  Trains running to/from London Paddington to Oxford and Cross Country to/from South only, using Platform No.4 at Oxford.  All other services still bus substitution.


Title: Re: Oxford Area Resignalling 2018
Post by: ray951 on July 16, 2018, 10:54:17
Does the stage 2 cover all the reversible signalling to Didcot?

Given that we are told that it takes a long time for drivers to learn routes how are they trained with the new signalling (and there is lots of it) given that the first trains only ran today and were service trains?




Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 16, 2018, 11:14:31
The train crew have a 78 page briefing document which fully describes the new signalling.  Then its down to actual familiarisation on site once its commissioned.

As I understand it, the reversible signalling is not commissioned until Stage 3.


Title: Re: Oxford Area Resignalling 2018
Post by: IndustryInsider on July 16, 2018, 12:02:34
The train crew have a 78 page briefing document which fully describes the new signalling.  Then its down to actual familiarisation on site once its commissioned.

As I understand it, the reversible signalling is not commissioned until Stage 3.

Yes, that's right.  All GWR drivers have (or will have) a briefing day to learn the many changes to signals and routes, and other TOC's/FOC's will have undertaken a similar approach.

I believe that the trains are using the new reversible signalling between Oxford's platform and Hinksey South Junction, but otherwise the full commissioning of all routes will be after next weekend.


Title: Re: Oxford Area Resignalling 2018
Post by: ray951 on July 16, 2018, 14:51:27
Stage 2 commissioned to plan today (16 July 2018).  Trains running to/from London Paddington to Oxford and Cross Country to/from South only, using Platform No.4 at Oxford.  All other services still bus substitution.
I commented earlier that I didn't understand why the Paddington to Oxford services couldn't stop at Didcot Parkway and I am even more confused now because it appears that there are 3 services each way that do stop at Didcot that is the 0527, 0616 and 0709 from Didcot and the 0540, 0631, 0724 from Oxford.
 
So does anyone know why they are making us catch us a bus when it seems to be perfectly possible to run a train service?


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 16, 2018, 15:15:16
I believe that the trains are using the new reversible signalling between Oxford's platform and Hinksey South Junction, but otherwise the full commissioning of all routes will be after next weekend.
Correct.  But I took the question to mean the reversible signalling to Didcot!  Between Hinksey South Junction and Oxford Platform No.4 trains are using the fully reversible signalled Down Oxford Main or Down Oxford Relief.


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 20, 2018, 07:21:08
Just a quick update (Friday 20/07/2018).  The resignalling seems to be progressing to plan.  Couple of minor non-critical signalling power supply snags and a problem with the Ascott-Under-Wychwood (Charlbury) fringe being sorted, but at the moment all looks reasonably OK for early Monday morning commissioning.


Title: Re: Oxford Area Resignalling 2018
Post by: IndustryInsider on July 20, 2018, 10:50:50
From my observations, the replacement bus services, whilst not ideal because they're buses of course and much slower, seem to have been very well organised again.  Plenty of staff at Oxford and Didcot, free water, shelter (from the sun, rather than rain this time!) at Oxford in the car park.

For me this once again demonstrates how good GWR are a running such planned disruptions and throws into sharp focus how bad they are at organising the more difficult unplanned ones!

I commented earlier that I didn't understand why the Paddington to Oxford services couldn't stop at Didcot Parkway and I am even more confused now because it appears that there are 3 services each way that do stop at Didcot that is the 0527, 0616 and 0709 from Didcot and the 0540, 0631, 0724 from Oxford.
 
So does anyone know why they are making us catch us a bus when it seems to be perfectly possible to run a train service?

I can only assume it's a lack of platform access at Didcot, given the extra services that are terminating and starting back from there?  I have to say though that it doesn't look like it would have been impossible to have stopped the trains there during week 2 to provide an hourly train service.


Title: Re: Oxford Area Resignalling 2018
Post by: MVR S&T on July 23, 2018, 01:14:34
Oxford area now on Open Train Times map, thers a LOT more capacity there!

https://www.opentraintimes.com/maps/signalling/oxford#T_OXFD



Title: Re: Oxford Area Resignalling 2018
Post by: martyjon on July 23, 2018, 06:43:13
Oxford area now on Open Train Times map, thers a LOT more capacity there!

https://www.opentraintimes.com/maps/signalling/oxford#T_OXFD

.... till there is a fault with the signalling system ....


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 23, 2018, 07:06:26
Stage 3 commissioned as planned (Monday 23 July 2018) and train services running again, now under control of the new signalling.  Haven't heard (yet) of any snags, but most schemes of this size usually have a few items deferred until a suitable time can be found to fix them.

Reminder: The Oxford area is closed again this coming weekend 28/29 July 2018 for some further work.


Title: Re: Oxford Area Resignalling 2018
Post by: IndustryInsider on July 23, 2018, 07:34:10
Yes, all working and so far going as planned.  The 05:17 to Reading was the first passenger train to use the new signalling, as the 05:14 to Worcester which should have been first left 8 minutes late.


Title: Re: Oxford Area Resignalling 2018
Post by: Gordon the Blue Engine on July 28, 2018, 09:53:32
It's interesting to watch OpenTrainTimes and see the new moves they can do now, eg parallel moves into P2 and P3, and quite a few down trains using the new Down Relief(?) from P4 to signal 2413 and undertaking Down Freights which can now run right up to signal 2415.

It looks like up trains from Hanborough could use the DM from Wolvercote Junction and go into P4, and thus allow a parallel move with up trains from Tackley into P3. Is this in fact true? 


Title: Re: Oxford Area Resignalling 2018
Post by: paul7575 on July 28, 2018, 11:06:07
It's interesting to watch OpenTrainTimes and see the new moves they can do now, eg parallel moves into P2 and P3, and quite a few down trains using the new Down Relief(?) from P4 to signal 2413 and undertaking Down Freights which can now run right up to signal 2415. 
It’s quite feasible that almost all down through passenger services will use that line.  If the points at the north end of the loop allow a reasonable speed it could be a faster route. 

I also noticed a Chiltern train towards Bicester leave the station via the crossovers onto the down through line.  It seemed to wait for a while before crossing back over at Oxford North Junction towards Oxford Parkway.  If necessary it could have been undertaken by a train using the outer line.


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 28, 2018, 17:28:12
It's interesting to watch OpenTrainTimes and see the new moves they can do now, eg parallel moves into P2 and P3, and quite a few down trains using the new Down Relief(?) from P4 to signal 2413 and undertaking Down Freights which can now run right up to signal 2415. 
It’s quite feasible that almost all down through passenger services will use that line.  If the points at the north end of the loop allow a reasonable speed it could be a faster route. 

I also noticed a Chiltern train towards Bicester leave the station via the crossovers onto the down through line.  It seemed to wait for a while before crossing back over at Oxford North Junction towards Oxford Parkway.  If necessary it could have been undertaken by a train using the outer line.

The Up and Down Relief Line points at Wolvercot Junction are both 90mph turnouts.

I understand that the remainder of the reversible signalling is being commissioned this weekend (28/29 July 2018).


Title: Re: Oxford Area Resignalling 2018
Post by: paul7575 on July 28, 2018, 18:11:39
It’s quite feasible that almost all down through passenger services will use that line.  If the points at the north end of the loop allow a reasonable speed it could be a faster route. 
The Up and Down Relief Line points at Wolvercot Junction are both 90mph turnouts.
Ah, that’s what I was hoping might be the case.  So crossing from P4 to the down through line immediately outside the station is presumably over a slower route than taking the direct alternative up to Wolvercot.  Perhaps ‘down relief’ isn’t the best name for it now, although there’s really not that much need for names to reflect exact usage...

Paul


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 28, 2018, 19:05:03
All of the crossovers at the North end of Oxford station are 25mph except entering Platform No.1 which is 20mph and to/from the sidings which is 15mph.  The Down Relief from Platform No.4 starts at 40mph, then rises to 65mph and finally 90mph by the time of Oxford North Junction.  So yes, its quicker to leave Platform No.4 along the Down Relief than turning out to the Down Main.


Title: Re: Oxford Area Resignalling 2018
Post by: IndustryInsider on July 29, 2018, 08:57:13
It looks like up trains from Hanborough could use the DM from Wolvercote Junction and go into P4, and thus allow a parallel move with up trains from Tackley into P3. Is this in fact true? 

Yes they can do that if they wish - and nothing is coming the other way!  Pretty much every line between Wolvercote Junction and Didcot North Junction is now bi-directional.  The only exceptions I can think of are the Up Oxford Relief and Down Oxford Relief between Oxford North Junction and Wolvercote and the Down Oxford between Appleford and Didcot North Junction.


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on July 29, 2018, 09:26:12
It looks like up trains from Hanborough could use the DM from Wolvercote Junction and go into P4, and thus allow a parallel move with up trains from Tackley into P3. Is this in fact true? 

Yes they can do that if they wish - and nothing is coming the other way!  Pretty much every line between Wolvercote Junction and Didcot North Junction is now bi-directional.  The only exceptions I can think of are the Up Oxford Relief and Down Oxford Relief between Oxford North Junction and Wolvercote and the Down Oxford between Appleford and Didcot North Junction.

Yes, the principle adopted in the design was that the Main Lines are all fully reversible but the Relief Lines only where operationally neccessary.


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on August 01, 2018, 12:46:57
A NR video of the trackwork carried out, down the page here: https://www.networkrail.co.uk/running-the-railway/our-routes/western/great-western-mainline/oxford/


Title: Re: Oxford Area Resignalling 2018
Post by: bobm on August 12, 2018, 13:09:38
Some photos showing the changes

(http://www.mbob.co.uk/rforum/oxfnjul14.jpg)
Looking north from Oxford in July 2014

(http://www.mbob.co.uk/rforum/oxfnaug18.jpg)
The same view in August 2018

And a couple of views to the south following the re-signalling works

(http://www.mbob.co.uk/rforum/oxfsaug18.jpg)

(http://www.mbob.co.uk/rforum/oxfsaug182.jpg)


Title: Re: Oxford Area Resignalling 2018
Post by: IndustryInsider on August 12, 2018, 15:24:43
The 25mph crossing north of Oxford station in the first two images was just about the only bit of track that wasn't replaced during the works.  The main route out of Platform 4 is now straight ahead on the Down Oxford Relief, but when it is renewed there would be the room for a faster turnout of 40mph to match the linespeed on the Down Oxford Relief for consistency.

The signalling continues to be operating reliably - the only major problem so far was a telecommunications one with the crossing phones. 

The bi-di signalling on Platform 4 has already proven very useful as I experienced first hand when trying to travel south last week and a terminating train had arrived in Platform 3 with no driver to take it into the sidings.  Four southbound trains were queuing outside the station within minutes, but rather than having to wait until the terminating train had cleared and all form an orderly queue to use platform 3, two of them were routed through Platform 4 instead.  Whilst it caused delays of 5-10 minutes that would have been much worse with the old signalling layout.


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on August 12, 2018, 16:08:35
That turnout stays as is for the Phase 2 layout at 25mph together with the 30mph entry and through speed for Platform No.4, suitable for terminating trains.  When the new Platform No.5 loop is added in Phase 2, that will have an entry, exit and through speed of 50mph, so would be the preference for through trains.


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on August 12, 2018, 16:12:34
Just noticed in BobMs photographs that those new signals have had their number etc. plates mounted outside the electrification protection cages, so will either have to be moved or an electrical isolation would be required to clean them..... ::)


Title: Re: Oxford Area Resignalling 2018
Post by: rower40 on August 13, 2018, 15:07:27
Just noticed in BobMs photographs that those new signals have had their number etc. plates mounted outside the electrification protection cages, so will either have to be moved or an electrical isolation would be required to clean them..... ::)
Yebbut they won't get so dirty without coal- or oil-fired traction units passing under them!


Title: Re: Oxford Area Resignalling 2018
Post by: IndustryInsider on August 13, 2018, 15:36:57
That turnout stays as is for the Phase 2 layout at 25mph together with the 30mph entry and through speed for Platform No.4, suitable for terminating trains.  When the new Platform No.5 loop is added in Phase 2, that will have an entry, exit and through speed of 50mph, so would be the preference for through trains.

Yes, it's far from urgent, just might make sense to up it to 40mph as and when that crossing becomes due for renewal given there is plenty of space.  Phase 2 (especially the Platform 5 element) will improve things further so hopefully won't get too bogged down in delays. 

Next on my shopping list would be a remodelled Wolvercote Junction redoubled as far as Handborough, with the Oxford Down Relief extended all the way to it to reduce conflicts further.


Title: Re: Oxford Area Resignalling 2018
Post by: SandTEngineer on August 13, 2018, 16:16:11
Well, for a change NR has planned ahead and the signalling design and Phase 1 site installation has allowed for that eventuality.


Title: Re: Oxford Area Resignalling 2018
Post by: charles_uk on August 31, 2018, 18:00:48
Passengers on the 15:22 Paddington to Great Malvern got to experience the benefits of the resignalling this afternoon.

As a result of a fault at the north end of Oxford station, the 15:22 was diverted onto platform 3, and then ran down to Wolvercote Junction on the up main (or whatever the correct terminology is!). Meanwhile, the 15:22 WOS:PAD ran towards Oxford on the up relief.

However, putting the Great Malvern train onto platform 3 at roughly the time the Paddington service was due did have an unfortunate but predictable consequence - there was an announcement on the 15:22 PAD:GMV advising passengers who thought they were on the Paddington train to change at Hanborough!

[edit to change one word]


Title: Re: Oxford Area Resignalling 2018
Post by: Dispatch Box on November 16, 2018, 19:44:49
Hello,

I Cannot wait to visit Oxford to see what they have done. My father was involved in the resignalling of oxford in 1973.



This page is printed from the "Coffee Shop" forum at http://gwr.passenger.chat which is provided by a customer of Great Western Railway. Views expressed are those of the individual posters concerned. Visit www.gwr.com for the official Great Western Railway website. Please contact the administrators of this site if you feel that content provided contravenes our posting rules ( see http://railcustomer.info/1761 ). The forum is hosted by Well House Consultants - http://www.wellho.net