Journey by Journey => North Downs Line => Topic started by: TonyN on January 11, 2021, 23:31:31



Title: Level crossing at Ash station to be replaced by bridge
Post by: TonyN on January 11, 2021, 23:31:31
Not sure if this has been on the forum before.

Quote
Guildford Borough Council (GBC) approved the application to build a bridge on Ash Road at its meeting on Wednesday (January 6), with work set to be completed in 2023.
https://www.getsurrey.co.uk/news/surrey-news/level-crossing-ash-station-replaced-19601746 (https://www.getsurrey.co.uk/news/surrey-news/level-crossing-ash-station-replaced-19601746)


Title: Re: Level crossing at Ash station to be replaced by bridge
Post by: FenMan on January 12, 2021, 13:42:15
Something not mentioned in the article is a planned footbridge between the platforms will make travel between Reading and Aldershot more attractive, with far more robust connections at Ash and a typical journey time of 50m.

The current arrangements are far from ideal, with passengers either risking a walk over the level crossing at Ash in the very short gaps between the NDL services and the Farnham - Guildfords (any minor delay can easily result in a 30 or 60 minute wait) or using the walking interchange between Ash Vale and North Camp.

Of course Reading - Aldershot passengers can also travel via Ascot (typical journey time 1h12m), but they may lose the will to live en route!


Title: Re: Level crossing at Ash station to be replaced by bridge
Post by: RichT54 on January 12, 2021, 16:57:54
The planning application can be found at the following link:

http://www2.guildford.gov.uk/publicaccess/applicationDetails.do?activeTab=summary&keyVal=_GUILD_DCAPR_187733 (http://www2.guildford.gov.uk/publicaccess/applicationDetails.do?activeTab=summary&keyVal=_GUILD_DCAPR_187733)

There are 236 documents associated with the application. The following link is to one of the documents (PDF) which shows the revised road layout and location of the bridge:

https://www2.guildford.gov.uk/publicaccess/files/CA6731046F63BD8B673188E1689330D8/pdf/19_P_01460-ASH_ROAD_BRIDGE_PROPOSED_DEVELOPMENT._ASHB-AEC-XX-XX-SK-CE-00065-1407938.pdf (https://www2.guildford.gov.uk/publicaccess/files/CA6731046F63BD8B673188E1689330D8/pdf/19_P_01460-ASH_ROAD_BRIDGE_PROPOSED_DEVELOPMENT._ASHB-AEC-XX-XX-SK-CE-00065-1407938.pdf)




Title: Re: Level crossing at Ash station to be replaced by bridge
Post by: RichT54 on March 06, 2022, 17:38:28
A recent report by Surrey Live says:

Quote
Ash level crossing closure costs set to rocket to £40m

A delayed scheme to close the Ash level crossing could now cost £40million, nearly double the original estimates.

Councillors heard at a meeting of Guildford Borough Council's overview and scrutiny committee on Tuesday (March 1) that works to replace the "dangerous" level crossing with a bridge were now likely to cost more because of delays approving the plans.

Councillor Fiona White (Liberal Democrat, Westborough) asked for an update on plans to replace the level crossing because of "huge amounts of development" taking place in the area and traffic levels increasing after the coronavirus pandemic, saying "the holdups are getting bad again."

Land to the south and east of Ash and Tongham was allocated for a total of 1,750 homes in the council's 2019 local plan.

Councillor John Rigg (Residents for Guildford and Villages, Holy Trinity), lead councillor for regeneration, said one of the first things he did when he took over the major projects portfolio was to look at costs, and that he found the cost of the bridge was "no longer £20m, it was likely closer to 40 million."


Quote
He added: "After an awful lot of negotiations, we got a grant of £23.7m. There's still a lot for us to find."

He said that delays approving the bridge on the Network Rail side were increasing the cost of the project.

No representative from Network Rail was present at the meeting, and the company has been contacted for comment.

Cllr Rigg said a "shortage of resources" and a recent meeting cancelled because of train cancellations during storms were causing delays but that council officers were "pressing them hard".

He asked: "How long will Network Rail take to approve a bridge, a simple straightforward bridge, designed by our expert consultants? How long is a piece of string? It's very disappointing."

Earlier in the meeting he had said: "We're delivering infrastructure for Surrey County Council, and to remove a dangerous level crossing for Network Rail.

"Neither are contributing to the cost. Network Rail, through delays in approving our bridge design, are causing serious concerns and cost price inflation."

According to an earlier council timeline, works on the bridge should have already started in the winter 2021/22, with a projected opening of spring/summer 2023.

A Network Rail spokesperson said: "Closing a level crossing is not a straightforward process and it always involves a lot of work for both ourselves and the local authorities.

"We are very pleased to be working with Guildford Borough Council to close this level crossing, which has a history of misuse by pedestrians. The proposed footbridge will also make it easier for passengers at Ash to change between services on the Alton and North Downs lines."


https://www.getsurrey.co.uk/news/surrey-news/ash-level-crossing-closure-costs-23275822 (https://www.getsurrey.co.uk/news/surrey-news/ash-level-crossing-closure-costs-23275822)



This page is printed from the "Coffee Shop" forum at http://gwr.passenger.chat which is provided by a customer of Great Western Railway. Views expressed are those of the individual posters concerned. Visit www.gwr.com for the official Great Western Railway website. Please contact the administrators of this site if you feel that content provided contravenes our posting rules ( see http://railcustomer.info/1761 ). The forum is hosted by Well House Consultants - http://www.wellho.net