Title: question about Landore viaduct at Swansea
Post by: infoman on March 20, 2023, 12:29:14
I have a date of 1978-1979 when most, if not all, the metal work was replaced although the supports are orginal.

Any further info would be much appreciated.


Title: Re: question about Landore viaduct at Swansea
Post by: Phantom on March 20, 2023, 12:56:57
I have a date of 1978-1979 when most, if not all, the metal work was replaced although the supports are orginal.

Any further info would be much appreciated.

Not sure if you have seen these John?

https://en.wikipedia.org/wiki/Landore_Viaduct

https://www.visitswanseabay.com/swansea-bay-at-home/doorstep-detectives/landore-viaduct/


Title: Re: question about Landore viaduct at Swansea
Post by: stuving on March 20, 2023, 13:20:10
I have a date of 1978-1979 when most, if not all, the metal work was replaced although the supports are orginal.

Any further info would be much appreciated.

What sort of thing do you want to know? I can find a couple of newspaper pieces from 1978, though 1979 is off the end of the archive!

Work started on June 12th 1978 on the westbound track at the Neath end, and was due to end at the other end in December, though the river bridge span was retained. All the wrought iron plate girders in the approach spans were replaced with modern steel, each span temporarily replaced by a "helper" for the half still in use.

The eastbound half was due to take from December until April 1979. Note that this was not a case of two separate structures, but the strength was in the girders underneath and half were swapped at a time. You can see now that there are rivetted plates joining the spans together in the middle, so presumably these were put in in situ.

The result was that the weight limit (RA) was increased, and the speed restriction went up from 20 to 40 mph.


Title: Re: question about Landore viaduct at Swansea
Post by: infoman on March 20, 2023, 18:02:33
Thank you both for your replys,

was the line shut into Swansea for the twelve months or was it done shutting one side and then the other or was bus replacement in operation?


Title: Re: question about Landore viaduct at Swansea
Post by: stuving on March 20, 2023, 18:58:57
was the line shut into Swansea for the twelve months or was it done shutting one side and then the other or was bus replacement in operation?

One side at a time, leaving a single line in use, but closed Sunday mornings (23:30-11:30) for the actual swapping over of the spans and supports. Most of the construction work was done with one line open. Some trains were, apparently, diverted and buses would run to Neath/Port Talbot. The main contractors were Redpath, Dorman, Long (Contracting) Limited and Adamson-Butterley Limited.

I'm guessing that the diverted trains would be ones that reversed in Swansea and went on via Llanelli, and were instead sent along the Briton Ferry line missing SWA.



This page is printed from the "Coffee Shop" forum at http://gwr.passenger.chat which is provided by a customer of Great Western Railway. Views expressed are those of the individual posters concerned. Visit www.gwr.com for the official Great Western Railway website. Please contact the administrators of this site if you feel that content provided contravenes our posting rules ( see http://railcustomer.info/1761 ). The forum is hosted by Well House Consultants - http://www.wellho.net