Train GraphicClick on the map to explore geographics
 
I need help
FAQ
Emergency
About .
Travel & transport from BBC stories as at 15:55 19 Apr 2024
- Mystery over woman's lying in road crash death
Read about the forum [here].
Register [here] - it's free.
What do I gain from registering? [here]
 02/06/24 - Summer Timetable starts
17/08/24 - Bus to Imber
27/09/25 - 200 years of passenger trains

On this day
19th Apr (1938)
Foundation, Beatties of London (link)

Train RunningCancelled
16:23 London Paddington to Oxford
18:00 Oxford to London Paddington
19:02 London Paddington to Bristol Temple Meads
19:23 London Paddington to Oxford
21:02 Oxford to London Paddington
Short Run
14:20 Paignton to Exmouth
15:50 Penzance to Gloucester
16:31 Barnstaple to Axminster
Delayed
13:15 Plymouth to London Paddington
PollsThere are no open or recent polls
Abbreviation pageAcronymns and abbreviations
Stn ComparatorStation Comparator
Rail newsNews Now - live rail news feed
Site Style 1 2 3 4
Next departures • Bristol Temple MeadsBath SpaChippenhamSwindonDidcot ParkwayReadingLondon PaddingtonMelksham
Exeter St DavidsTauntonWestburyTrowbridgeBristol ParkwayCardiff CentralOxfordCheltenham SpaBirmingham New Street
April 19, 2024, 16:00:40 *
Welcome, Guest. Please login or register.

Login with username, password and session length
Forgotten your username or password? - get a reminder
Most recently liked subjects
[269] Rail to refuge / Travel to refuge
[101] Rail delay compensation payments hit £100 million
[44] Difficult to argue with e-bike/scooter rules?
[41] Signage - not making it easy ...
[8] IETs at Melksham
[7] Ferry just cancelled - train tickets will be useless - advice?
 
News: the Great Western Coffee Shop ... keeping you up to date with travel around the South West
 
   Home   Help Search Calendar Login Register  
Pages: [1]
  Print  
Author Topic: Electrification confirmed  (Read 10755 times)
paul7575
Transport Scholar
Hero Member
******
Posts: 5318


View Profile
« on: July 16, 2012, 09:47:00 »

...in this mornings HLOS (High Level Output Specification):

http://assets.dft.gov.uk/publications/hlos-2012/railways-act-2005.pdf

To be 25kV OHLE as generally expected, but the extra surprise is that it carries on to Southampton, as part of a major north south electrified freight route. Change from DC (Direct Current) to AC to be used as a trial section for a progressive update of the rest of the 'Southern'...   Shocked

Paul
Logged
Electric train
Transport Scholar
Hero Member
******
Posts: 4362


The future is 25000 Volts AC 750V DC has its place


View Profile
« Reply #1 on: July 16, 2012, 13:13:58 »

...in this mornings HLOS (High Level Output Specification):

http://assets.dft.gov.uk/publications/hlos-2012/railways-act-2005.pdf

To be 25kV OHLE as generally expected, but the extra surprise is that it carries on to Southampton, as part of a major north south electrified freight route. Change from DC (Direct Current) to AC to be used as a trial section for a progressive update of the rest of the 'Southern'...   Shocked

Paul

The concept for has been in development for over a year.  There are a number of reasons other than a trial conversion the third rail traction substation equipment and high voltage supply network Basingstoke to Bournemouth is life expired, although installed in the 1960 some of the kit had been in storage for a number of years before it was used (originally intended for the East Grinsted electrification) also it does not have the capacity as it stands today for much in the way of electrically hauled freight and increased electric traction (cross country) passenger services
Logged

Starship just experienced what we call a rapid unscheduled disassembly, or a RUD, during ascent,”
IndustryInsider
Data Manager
Hero Member
******
Posts: 10116


View Profile
« Reply #2 on: July 16, 2012, 17:21:43 »

What does this mean for services out of Waterloo heading to Southampton, Bournemouth and Basingstoke I wonder?

Presumably all SWT (South West Trains)'s Class 444 Desiro's (and some of their 450s?) are going to get a pantograph and dual traction equipment fitted and will run 3rd rail London to Basingstoke, 25kv from Basingstoke to Southampton and back to 3rd rail from there to Weymouth?  Or will there be a new build of dual traction EMUs (Electric Multiple Unit)?  Either way it begs the question of what will happen to the many trains that don't currently stop at Basingstoke, as presumably they won't be able to change traction on the move?
Logged

To view my GWML (Great Western Main Line) Electrification cab video 'before and after' video comparison, as well as other videos of the new layout at Reading and 'before and after' comparisons of the Cotswold Line Redoubling scheme, see: http://www.dailymotion.com/user/IndustryInsider/
Electric train
Transport Scholar
Hero Member
******
Posts: 4362


The future is 25000 Volts AC 750V DC has its place


View Profile
« Reply #3 on: July 16, 2012, 17:51:57 »

What does this mean for services out of Waterloo heading to Southampton, Bournemouth and Basingstoke I wonder?

Presumably all SWT (South West Trains)'s Class 444 Desiro's (and some of their 450s?) are going to get a pantograph and dual traction equipment fitted and will run 3rd rail London to Basingstoke, 25kv from Basingstoke to Southampton and back to 3rd rail from there to Weymouth?  Or will there be a new build of dual traction EMUs (Electric Multiple Unit)?  Either way it begs the question of what will happen to the many trains that don't currently stop at Basingstoke, as presumably they won't be able to change traction on the move?

444 and 450 are from a dual system family therefore they could be converted, equally they could be cascaded and new stock used.  My guess, the wires will not stop at Southampton, the 1980's electrification west of Bournemouth is weak to enhance the traction power supply (TPH (trains per hour) conversion to substations) would require upgrading the 11kV supply network to 33kV which is costed at ^2m per site converted and that does not include any works required at Grid feed sites and installing high voltage cables along side the track.
Logged

Starship just experienced what we call a rapid unscheduled disassembly, or a RUD, during ascent,”
paul7575
Transport Scholar
Hero Member
******
Posts: 5318


View Profile
« Reply #4 on: July 16, 2012, 18:35:01 »

444 and 450 are from a dual system family therefore they could be converted, equally they could be cascaded and new stock used.  

It's not really a question of 'conversion', they are already wired and just need the relevant big lumps of hardware fitting.  There are clues in the cabs already, such as the control switches for raising the pantograph.  More a case of finishing them off completely...

Paul
Logged
Electric train
Transport Scholar
Hero Member
******
Posts: 4362


The future is 25000 Volts AC 750V DC has its place


View Profile
« Reply #5 on: July 16, 2012, 19:15:47 »

444 and 450 are from a dual system family therefore they could be converted, equally they could be cascaded and new stock used.  

It's not really a question of 'conversion', they are already wired and just need the relevant big lumps of hardware fitting.  There are clues in the cabs already, such as the control switches for raising the pantograph.  More a case of finishing them off completely...

Paul
Agreed, it is likely to be a little more than bolt a pan onto the roof, I am not sure if they have transformers fitted and there are a few other items that need bolting on and then the traction control software Ctr-alt-del  Grin
Logged

Starship just experienced what we call a rapid unscheduled disassembly, or a RUD, during ascent,”
IndustryInsider
Data Manager
Hero Member
******
Posts: 10116


View Profile
« Reply #6 on: July 16, 2012, 19:27:04 »

It's not really a question of 'conversion', they are already wired and just need the relevant big lumps of hardware fitting.  There are clues in the cabs already, such as the control switches for raising the pantograph.  More a case of finishing them off completely...

Ah, that's good then.  I knew that one of the coaches in each set already had a recess in the roof for a pantograph, but didn't realise that cab controls were fitted.  Any answers to my Basingstoke conundrum though?
Logged

To view my GWML (Great Western Main Line) Electrification cab video 'before and after' video comparison, as well as other videos of the new layout at Reading and 'before and after' comparisons of the Cotswold Line Redoubling scheme, see: http://www.dailymotion.com/user/IndustryInsider/
Electric train
Transport Scholar
Hero Member
******
Posts: 4362


The future is 25000 Volts AC 750V DC has its place


View Profile
« Reply #7 on: July 16, 2012, 20:19:51 »

  Any answers to my Basingstoke conundrum though?

AC / DC (Direct Current) change over where needed.  With modern signaling and fiber optic telecoms and the right location they are quite simple to implement
Logged

Starship just experienced what we call a rapid unscheduled disassembly, or a RUD, during ascent,”
paul7575
Transport Scholar
Hero Member
******
Posts: 5318


View Profile
« Reply #8 on: July 16, 2012, 20:45:41 »

Changeover on the move is possible, and at fairly high speed.  Eurostars did it at about 90 mph when they left CTRL (Channel Tunnel Rail Link)/HS1 (High Speed line 1 - St Pancras to Channel Tunnel) for the route round to Waterloo - Fawkham Jn I think. 

However it may be easier to do it during a stop anyway - probably cuts down the length of the dual section as well.  LO 378s are now routinely doing moving changeovers on the WLL by the way.

In the specific case of Basingstoke, it is only 1 train each way per hour non-stops, so adding that stop wouldn't exactly kill the timetable...

Paul
Logged
IndustryInsider
Data Manager
Hero Member
******
Posts: 10116


View Profile
« Reply #9 on: July 16, 2012, 20:48:59 »

Point taken, though I doubt SHRUG will be too impressed!  It's also more than 1tph in the peak hours where in one hour no less than four up trains don't stop there.  Perhaps a high-speed changeover on the move can be installed as you suggest?
Logged

To view my GWML (Great Western Main Line) Electrification cab video 'before and after' video comparison, as well as other videos of the new layout at Reading and 'before and after' comparisons of the Cotswold Line Redoubling scheme, see: http://www.dailymotion.com/user/IndustryInsider/
Do you have something you would like to add to this thread, or would you like to raise a new question at the Coffee Shop? Please [register] (it is free) if you have not done so before, or login (at the top of this page) if you already have an account - we would love to read what you have to say!

You can find out more about how this forum works [here] - that will link you to a copy of the forum agreement that you can read before you join, and tell you very much more about how we operate. We are an independent forum, provided and run by customers of Great Western Railway, for customers of Great Western Railway and we welcome railway professionals as members too, in either a personal or official capacity. Views expressed in posts are not necessarily the views of the operators of the forum.

As well as posting messages onto existing threads, and starting new subjects, members can communicate with each other through personal messages if they wish. And once members have made a certain number of posts, they will automatically be admitted to the "frequent posters club", where subjects not-for-public-domain are discussed; anything from the occasional rant to meetups we may be having ...

 
Pages: [1]
  Print  
 
Jump to:  

Powered by MySQL Powered by PHP Powered by SMF 1.1.2 | SMF © 2006-2007, Simple Machines LLC Valid XHTML 1.0! Valid CSS!
This forum is provided by customers of Great Western Railway (formerly First Great Western), and the views expressed are those of the individual posters concerned. Visit www.gwr.com for the official Great Western Railway website. Please contact the administrators of this site if you feel that the content provided by one of our posters contravenes our posting rules (email link to report). Forum hosted by Well House Consultants

Jump to top of pageJump to Forum Home Page