Train GraphicClick on the map to explore geographics
 
I need help
FAQ
Emergency
About .
Travel & transport from BBC stories as at 13:15 28 Mar 2024
- How do I renew my UK passport and what is the 10-year rule?
* Man held over stabbing in front of train passengers
- Easter travel warning as millions set to hit roads
Read about the forum [here].
Register [here] - it's free.
What do I gain from registering? [here]
 02/06/24 - Summer Timetable starts
17/08/24 - Bus to Imber
27/09/25 - 200 years of passenger trains

On this day
28th Mar (1917)
Bideford, Westward Ho! and Appledore closed (link)

Train RunningCancelled
11:23 Weston-Super-Mare to London Paddington
11:50 Cardiff Central to London Paddington
12:15 London Paddington to Cardiff Central
12:30 London Paddington to Weston-Super-Mare
13:00 Bristol Temple Meads to London Paddington
13:15 Swindon to Westbury
13:26 Weston-Super-Mare to London Paddington
13:30 London Paddington to Bristol Temple Meads
14:19 Westbury to Swindon
15:14 Swindon to Westbury
Short Run
08:03 London Paddington to Penzance
10:35 London Paddington to Exeter St Davids
10:55 Paignton to London Paddington
11:23 Portsmouth Harbour to Cardiff Central
11:48 London Paddington to Carmarthen
12:03 London Paddington to Penzance
12:12 Salisbury to Bristol Temple Meads
12:42 Bristol Temple Meads to Salisbury
12:46 Avonmouth to Weston-Super-Mare
13:03 London Paddington to Plymouth
13:07 Salisbury to Bristol Temple Meads
13:10 Gloucester to Weymouth
13:26 Okehampton to Exeter Central
14:05 Salisbury to Bristol Temple Meads
16:19 Carmarthen to London Paddington
Delayed
10:04 London Paddington to Penzance
10:23 Portsmouth Harbour to Cardiff Central
11:29 Weymouth to Gloucester
11:30 Cardiff Central to Portsmouth Harbour
12:27 Okehampton to Exeter Central
12:28 Plymouth to Gunnislake
12:30 Cardiff Central to Portsmouth Harbour
14:30 Cardiff Central to Portsmouth Harbour
PollsOpen and recent polls
Closed 2024-03-25 Easter Escape - to where?
Abbreviation pageAcronymns and abbreviations
Stn ComparatorStation Comparator
Rail newsNews Now - live rail news feed
Site Style 1 2 3 4
Next departures • Bristol Temple MeadsBath SpaChippenhamSwindonDidcot ParkwayReadingLondon PaddingtonMelksham
Exeter St DavidsTauntonWestburyTrowbridgeBristol ParkwayCardiff CentralOxfordCheltenham SpaBirmingham New Street
March 28, 2024, 13:33:56 *
Welcome, Guest. Please login or register.

Login with username, password and session length
Forgotten your username or password? - get a reminder
Most recently liked subjects
[142] West Wiltshire Bus Changes April 2024
[80] would you like your own LIVE train station departure board?
[56] Return of the BRUTE?
[46] If not HS2 to Manchester, how will traffic be carried?
[43] Infrastructure problems in Thames Valley causing disruption el...
[34] Reversing Beeching - bring heritage and freight lines into the...
 
News: the Great Western Coffee Shop ... keeping you up to date with travel around the South West
 
   Home   Help Search Calendar Login Register  
Pages: [1]
  Print  
Author Topic: Reliability, Reliability, Reliability  (Read 3883 times)
grahame
Administrator
Hero Member
*****
Posts: 40690



View Profile WWW Email
« on: August 17, 2019, 06:40:39 »

Our mini-survey at http://www.passenger.chat/22054 brought reliabiity up as the most important factor you consider when you elect to travel by train. And I took the libery of reminding the group at yesterday's timetable "snagging" meeting of that prior to December - for goodness sake get it reliable. The point was brought home when the Transport Focus rep at the meeting followed up to confirm that our results mirror their nationwide findings. So, yes, it will be nice to speed up the trains but for goodness sake please don't do so at the expense of reliabiity!

Put another way ...

1: Reliability
2: Reliability
3: Reliability

So - how do you do that?

1. Design for reliable performance in the first place
2. Preventative maintenance so that less goes wrong
3. Improve mitigation so that you can deal with issues quickly and with less damage

Big problem ... no single cause of reliabiity problems ... so no easy solution.
* This is due to a tree blocking the railway earlier today.
* This is due to a shortage of train crew.
* This is due to a fault on this train.
* This is due to more trains than usual needing repairs at the same time.
* This is due to congestion
* This is due to severe weather
* This is due to a fault with the signalling system.
* This is due to overcrowding.
* This is due to passengers causing a disturbance on this train.

But "design for reliable performance in the first place" for TOCs (Train Operating Company) means
* Having enough trains to run the services you schedule
* Have enough staff to run the services you schedule
* Only schedule services that will fit on the tracks

"Enough trains" may mean hot spares and / or multiple unit trains that can be reduced to single unit trains
"Enough staff" may mean a pool of operational-capable staff performing important but not urgent tasks on all shifts and geographically widely spread
"Enough tracks" may mean not cramming things in - a smidgin fewer, but a smidgin longer, trains.

I have no doubt (I know) that GWR (Great Western Railway) are putting huge planning into December's timetable change; I really hope that enthusiasm for improved schedules (frequency and speed) in many parts of the network hasn't lead to any over-rosy views of how well things might work.  Teething problems no doubt - please, mr GWR, ensure you've got a plan to nip them in the bud so that we have not only frequency and speed but also the top passenger want of reliability.
Logged

Coffee Shop Admin, Acting Chair of Melksham Rail User Group, Option 24/7 Melksham Rep
Adrian
Transport Scholar
Sr. Member
******
Posts: 171


View Profile
« Reply #1 on: August 17, 2019, 07:27:58 »

Running a 'right time' railway is, of course, crucial to running a reliable railway.  With trains and crews used so intensively, turnbacks short of the final destination and skipping stops means cancellations for the customers affected.

As well as having the necessary resources available - trains, track and staff - the timetable needs to be designed as far as possible so that a 5 minute delay on one service doesn't delay several others, causing trains to lose their paths elsewhere, and spiralling knock-on effects.  Since Network Rail determine the fine detail of the timetable and make signalling decisions, I think they are ultimately the ones who must answer to this.

A good example of a line where delays quickly multiply is Bristol to Taunton due to the mix of fast and stopping services and single-track Weston Loop and junctions either end.  Often it is a late-running westbound Cross-country service to that starts the rot.  It passes Uphill Junction late, so a Cardiff - Taunton can't come off the Weston Loop, so the next Taunton - Cardiff is held on the main line because it can't go onto the Weston Loop, and possibly a fast service then gets stuck behind that.  And then the delayed Cardiff - Taunton has a short turnaround time and is consequently late coming back.

What can GWR (Great Western Railway) do to avoid situations like this, when the factors are largely outside their control?  XC (Cross Country Trains (franchise)) not running on time, insufficient pathing margin in the timetable, and a restrictive track layout at Uphill Junction?  It would be good to see CP6 (Control Period 6 - The five year period between 2019 and 2024) used to improve resilience at points in the network where conflicts like this frequently arise.  Bristol East is another.  I think it's less about adding extra tracks but allowing untangling the paths that cross with each other.
Logged
TaplowGreen
Transport Scholar
Hero Member
******
Posts: 7743



View Profile
« Reply #2 on: August 17, 2019, 08:12:36 »


I have no doubt (I know) that GWR (Great Western Railway) are putting huge planning into December's timetable change; I really hope that enthusiasm for improved schedules (frequency and speed) in many parts of the network hasn't lead to any over-rosy views of how well things might work.  Teething problems no doubt - please, mr GWR, ensure you've got a plan to nip them in the bud so that we have not only frequency and speed but also the top passenger want of reliability.

Graham - given that you're "in the know" in respect of planning, what measures are GWR taking to ensure that the endemic crew shortage situation is resolved in good time for the introduction of the new timetable, when additional services will make more demands of the workforce?

You've listed a number of potential issues which can jeopardise reliability, the first problems a business should usefully address are those which are within its control to influence, as the provision of adequate staff is 100% within GWR's responsibility and accountability I'd be interested in the nature of the ongoing planning to ensure that the requirement to provide adequate staff to run all timetabled services is going to be met.
Logged
Red Squirrel
Administrator
Hero Member
*****
Posts: 5190


There are some who call me... Tim


View Profile
« Reply #3 on: August 17, 2019, 11:06:57 »

...
A good example of a line where delays quickly multiply is Bristol to Taunton due to the mix of fast and stopping services and single-track Weston Loop and junctions either end.  Often it is a late-running westbound Cross-country service to that starts the rot.  It passes Uphill Junction late, so a Cardiff - Taunton can't come off the Weston Loop, so the next Taunton - Cardiff is held on the main line because it can't go onto the Weston Loop, and possibly a fast service then gets stuck behind that.  And then the delayed Cardiff - Taunton has a short turnaround time and is consequently late coming back.
...

...and I'm sure we can all think of other examples where singling has led to a lack of resilience. When lines are singled to save money, their capacity is not halved - it is reduced by one or more orders of magnitude.
Logged

Things take longer to happen than you think they will, and then they happen faster than you thought they could.
eightf48544
Transport Scholar
Hero Member
******
Posts: 4574


View Profile Email
« Reply #4 on: August 17, 2019, 17:20:29 »

Good points by Adrian and Red Squirrel. Maybe before we look at squeezing extra trains onto the line, we should look at the existing service firstly to see what the  bottlenecks are that prevent them it running reliably. These are mostly well known and if possible iron those out. Secondly look to see if the capacity of the proposed extra train can served by lengthening one of more of the existing trains. These suggestions mainly apply to peak services.

Thirdly if it not possible to sort out the bottle necks then and it is not possible to add capacity to the existing service then Capital Works will be required, but hopefully with a god business case.

It should provided as has been said there is sufficient rolling stock and train crews be possible to slot in an extra train on  most lines in off the peak hours. Particularly first and last trains.
Logged
grahame
Administrator
Hero Member
*****
Posts: 40690



View Profile WWW Email
« Reply #5 on: August 17, 2019, 18:58:03 »

Graham - given that you're "in the know" in respect of planning, what measures are GWR (Great Western Railway) taking to ensure that the endemic crew shortage situation is resolved in good time for the introduction of the new timetable, when additional services will make more demands of the workforce?

You used the word "ensure" there - and in the following paragraph too.  I know of a lot of activities which are being undertaken to address the issues, but their sufficiency to ensure  - well - I don't know how much they are doing everything they can / spare no expense, and how much they are taking steps but ruled too much by accountants to give the firmness of "ensure"ance.

There was been a major campaign of staff recruitment and training.  There are significant depot developments / improvements underway.  There is a plan in place that means that when the 143s go, there should be more Castles back from Wabtec. A plan for 769s to come in to send more turbos west.  Sums that suggest there should be enough  IETs (Intercity Express Train).  And it's all written up (it has been for a while) with some waypoints to measure.   I'm sounding a bit like the GWR publicity machine as I write that up, aren't I?   But back to "address" - I don't know if it will ensure.

I'm also very much aware that GWR are dependent on so many others ... they are just one element in a complex and symbiotic relationship which both works and and frustrates, and makes for so much smoke and mirrors that where the buck stops is pretty unclear to us passengers .. and I suspect to some of the people who work in the industry too.

Let's see how it goes.  I really don't know.  But I know we've got some darned good people trying, and they're sometimes between a rock and a hard place in compromising, compounded by being swamped by the occasional - or not so occasional - unexpected wave.
Logged

Coffee Shop Admin, Acting Chair of Melksham Rail User Group, Option 24/7 Melksham Rep
IndustryInsider
Data Manager
Hero Member
******
Posts: 10095


View Profile
« Reply #6 on: August 17, 2019, 21:17:44 »

In terms of crew, I would expect the first couple of weeks to be stretching availability on the run up to Christmas, then as of new year there should be few problems for the first three and a half months until Easter, as there’s usually plenty of spare driver capacity. 

So for me it largely hinges on our levels of preparedness for Easter onwards.
Logged

To view my GWML (Great Western Main Line) Electrification cab video 'before and after' video comparison, as well as other videos of the new layout at Reading and 'before and after' comparisons of the Cotswold Line Redoubling scheme, see: http://www.dailymotion.com/user/IndustryInsider/
eightonedee
Transport Scholar
Hero Member
******
Posts: 1532



View Profile
« Reply #7 on: August 17, 2019, 21:21:46 »

One looming issue is the reliance on delivery of the 769s and that they work when they arrive. The delivery date is drifting backwards, and there is a worrying lack of information on the internet about any of them having entered service on Northern or in Wales, both of which I think were due to have them before GWR (Great Western Railway). I may be jumping to conclusions, but are there problems with the conversion?

Will sufficient units be available to be held back on lease to cover any delays or problems?
Logged
IndustryInsider
Data Manager
Hero Member
******
Posts: 10095


View Profile
« Reply #8 on: August 17, 2019, 21:30:33 »

The December timetable plan can be delivered without them I believe, though it will prevent further Turbo cascades.  The Cardiff-Pompey 5-car service should still happen, but perhaps other trains won’t be as long as GWR (Great Western Railway) was hoping initially.
Logged

To view my GWML (Great Western Main Line) Electrification cab video 'before and after' video comparison, as well as other videos of the new layout at Reading and 'before and after' comparisons of the Cotswold Line Redoubling scheme, see: http://www.dailymotion.com/user/IndustryInsider/
grahame
Administrator
Hero Member
*****
Posts: 40690



View Profile WWW Email
« Reply #9 on: August 17, 2019, 21:33:19 »

The December timetable plan can be delivered without them I believe, though it will prevent further Turbo cascades.  The Cardiff-Pompey 5-car service should still happen, but perhaps other trains won’t be as long as GWR (Great Western Railway) was hoping initially.

That coincides with what I heard.  Also heard that no 769s are out yet because of a glitch (or glitches) in the design process ... there is confidence that once it / they are overcome the actual work will be fast (at least in railway terms).
Logged

Coffee Shop Admin, Acting Chair of Melksham Rail User Group, Option 24/7 Melksham Rep
TaplowGreen
Transport Scholar
Hero Member
******
Posts: 7743



View Profile
« Reply #10 on: August 18, 2019, 09:04:46 »

In terms of crew, I would expect the first couple of weeks to be stretching availability on the run up to Christmas, then as of new year there should be few problems for the first three and a half months until Easter, as there’s usually plenty of spare driver capacity. 

So for me it largely hinges on our levels of preparedness for Easter onwards.

Thanks II.

Anyone looking at the number of cancellations due to crew shortage today (more being added all the time it seems), and on a daily basis for at least the last month, will not be inspired with confidence of GWRs (Great Western Railway) ability to get control of this issue in respect of the current timetable, never mind a new and more ambitious one.
« Last Edit: August 18, 2019, 09:10:07 by TaplowGreen » Logged
Do you have something you would like to add to this thread, or would you like to raise a new question at the Coffee Shop? Please [register] (it is free) if you have not done so before, or login (at the top of this page) if you already have an account - we would love to read what you have to say!

You can find out more about how this forum works [here] - that will link you to a copy of the forum agreement that you can read before you join, and tell you very much more about how we operate. We are an independent forum, provided and run by customers of Great Western Railway, for customers of Great Western Railway and we welcome railway professionals as members too, in either a personal or official capacity. Views expressed in posts are not necessarily the views of the operators of the forum.

As well as posting messages onto existing threads, and starting new subjects, members can communicate with each other through personal messages if they wish. And once members have made a certain number of posts, they will automatically be admitted to the "frequent posters club", where subjects not-for-public-domain are discussed; anything from the occasional rant to meetups we may be having ...

 
Pages: [1]
  Print  
 
Jump to:  

Powered by MySQL Powered by PHP Powered by SMF 1.1.2 | SMF © 2006-2007, Simple Machines LLC Valid XHTML 1.0! Valid CSS!
This forum is provided by customers of Great Western Railway (formerly First Great Western), and the views expressed are those of the individual posters concerned. Visit www.gwr.com for the official Great Western Railway website. Please contact the administrators of this site if you feel that the content provided by one of our posters contravenes our posting rules (email link to report). Forum hosted by Well House Consultants

Jump to top of pageJump to Forum Home Page