Knew there were a few Platform ZERO around, knew of the Zero at Cardiff, didn't know where the others were.
LEEDS is about to join them ... from
the Yorkshire PostNew picture shows Leeds Station platform zero as hundreds of workers give up Christmas to finish GBP161m job
Hundreds of workers have given up their Christmases with their families to complete a major GBP161million investment to build a new platform at Leeds station.
[snip]
Over the final two-and-a-half days of work, final work to the overhead lines, track and signalling systems will take place, as well as rigorous testing to make sure the platform is ready for train services.
While the platform won't come into full use until the May 2021 timetable change, it will be available for trains to use during times of disruption, helping to minimise delays for passengers.
Next ... Chippenham? Platform face there already ... "just" need the track!