With the rumours that the electrification TV▸ branches is being delayed I wonder if they'll be left as diesel enclaves.
Where have you heard that?
Well, the
CP5▸ Enhancement Delivery Plan always had this caveat under all the timetables for
GW» electrification:
It should be noted that an efficient profiling workstream is considering all electrification
projects and the outcome of this workstream may result in reprofiling the delivery dates of
some electrification projects.
The September 2014 update replaces the
GRIP▸ 6 milestones by Entry Into Service and First Electric Train (i.e. timetable change). For the first two stages the dates reflect the previous target dates but now
EIS▸ is a regulated Output:
MAI▸ to BWP (EIS in June for December 2016) and
CPM» to
BRI» (EIS and FET May 2017). The dates post GRIP 3 for Filton Bank are still indicative. The TV branches are in another project, to which Southcote to Basingstoke has been added - all dates post GRIP 3 indicative, and for Basingstoke they are TBA.
So completing the branches later has always been foreseen as planning wiggle room, and might not even count as a delay.