| Re: Network Rail Enhancements plan (what is being done and target date) Posted by stuving at 10:08, 24th March 2026 | ![]() ![]() ![]() |
March 2026 enhancements plan with estimated target dates
https://www.networkrail.co.uk/wp-content/uploads/2020/01/CP7-Enhancements-Delivery-Plan-Mar-2026-Update.pdf
https://www.networkrail.co.uk/wp-content/uploads/2020/01/CP7-Enhancements-Delivery-Plan-Mar-2026-Update.pdf
That link is one of those self-garbling ones*. But the URL as displayed works:
https://www.networkrail.co.uk/wp-content/uploads/2020/01/CP7-Enhancements-Delivery-Plan-Mar-2026-Update.pdf
* Actually the link inside the quote works too - it's just the original that 404s!
| Network Rail Enhancements plan (what is being done and target date) Posted by John D at 07:54, 24th March 2026 | ![]() ![]() ![]() |
March 2026 enhancements plan with estimated target dates
https://www.networkrail.co.uk/wp-content/uploads/2020/01/CP7-Enhancements-Delivery-Plan-Mar-2026-Update.pdf
Some selected items for GWR area (more details on document)
Oxfordshire Connect (capacity & time improvements) March 2029
Cardiff Central station modernisation March 2030
Acton West - Acton Wells (known as Poplar lines) electrification July 2026
Metrowest phase 1b (Portishead line) December 2028